Escalation Factors for WY PRA-YELL 10(15), Grand Loop Road (Madison to Norris – Segment B)

Latest Month: October 2009
Fuel Price: 2.13
Asphalt Price: 502.65

Computation of Contract Base Price Indexes
Asphalt Cement Adjustment
The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.
Week EndingAsphalt  ($/metric ton)
Base Price Index564.93

Fuel Price Adjustment
The Base Price Index (BPI) is a price index determined by arithmetic average of OPIS publications' daily rack prices on a weekly basis for the 4 weeks preceding the bid opening.
Week EndingFuel  ($/gallon)
Base Price Index1.29


Archived Months for 2009
MonthFuelAsphalt
February1.40633.82
March1.39613.15
April1.69585.60
May1.62534.62
June1.84523.59
July1.82523.59
August2.03520.84
September2.08518.08

   


Home | About WFLHD | Projects | Procurement | Design Resources | Contact Information

USDOT | FHWA | FLHP | EFLHD | CFLHD | WFLHD

Please send your questions or comments to webmaster@mail.wfl.fhwa.dot.gov
Last update: November 3, 2009