Western Federal Lands Highway Division The edge of a forest along the horizon
About WFLHD Projects Procurement Design Resources A highway stretching off into the distance

  Location: Home > Construction Resources > Escalation Factors





 
Related Links
Acronym List
Privacy Policy
Site Map

Escalation Factors for MT PHF 59-1(2) and WY PRA-YELL 12(5),
Beartooth Highway and Yellowstone National Park Northeast Entrance Road

Latest Month: October 2009
Fuel Price: 2.09
Asphalt Price: 520.84

Computation of Contract Base Price Indexes
Asphalt Cement Adjustment
The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.
4 Week AverageAsphalt  ($/metric ton)
Base Price Index362.38

Fuel Price Adjustment
The Base Price Index (BPI) is a price index determined by arithmetic average of OPIS publications' daily rack prices on a weekly basis for the 4 weeks preceding the bid opening.
28 Day AverageFuel  ($/gallon)
Base Price Index2.28


Archived Months for 2007
MonthFuelAsphalt
June2.30354.94
July2.42347.22
August2.38349.98
September2.53348.60
October2.75341.71
November3.08330.69
December2.89330.69

Archived Months for 2008
MonthFuelAsphalt
January2.73332.07
February2.80336.20
March3.31342.40
April3.54355.49
May3.74428.24
June3.90475.37
July3.92688.94
August3.67771.61
September3.49738.54
October2.88637.88
November2.12620.04
December1.42604.61

Archived Months for 2009
MonthFuelAsphalt
January1.65594.69
February1.47575.95
March1.34578.02
April1.57578.71
May1.62574.30
June1.85567.68
July1.82564.38
August2.01538.75
September2.06531.86

   


Home | About WFLHD | Projects | Procurement | Design Resources | Contact Information

USDOT | FHWA | FLHP | EFLHD | CFLHD | WFLHD

Please send your questions or comments to webmaster@mail.wfl.fhwa.dot.gov
Last update: November 3, 2009