Escalation Factors for ID PFH 22-1(11), Cascade - Warm Lake Road

Latest Month: March 2009
Fuel Price: 1.39
Asphalt Price: 633.82

Computation of Contract Base Price Indexes
Asphalt Cement Adjustment
The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.
4 Week AverageAsphalt  ($/metric ton)
Base Price Index509.81

Fuel Price Adjustment
The Base Price Index (BPI) is a price index determined by arithmetic average of OPIS publications daily rack prices for the 28 calendar days preceding the bid opening.
28 Day AverageFuel  ($/gallon)
Base Price Index3.5664


Archived Months for 2008
MonthFuelAsphalt
May3.93545.64
June4.10651.05
July4.11799.17
August3.68909.40
September3.36947.29
October2.88829.48
November2.09661.38
December1.61647.60

Archived Months for 2009
MonthFuelAsphalt
January1.67620.04
February1.47620.04

   


Home | About WFLHD | Projects | Procurement | Design Resources | Contact Information

USDOT | FHWA | FLHP | EFLHD | CFLHD | WFLHD

Please send your questions or comments to webmaster@mail.wfl.fhwa.dot.gov
Last update: October 1, 2009