Escalation Factors for Glacier National Park Projects Prices for Latest Month
Month: October 2009Fuel Price: 2.12 Asphalt Price: 472.50 Base Price Indexes Listed by Project Base Price Index Computation Methods
Asphalt Cement Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.Fuel Price Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average of OPIS publications daily rack prices for the 28 calendar days preceding the bid opening. MT PRA GLAC 10 (23), GTSR Rehabilitation – Big Bend to Logan Pass, Phase VIII
Data for Archived Months Archived Months for 2009
|
|||||||||||||||||||||||||||||||||||
|