Escalation Factors for ID PFH 60-1(3), Salmon River Road

Latest Month: July 2008
Fuel Price: 4.11
Asphalt Price: 799.17

Computation of Contract Base Price Indexes
Asphalt Cement Adjustment
The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.
4 Week AverageAsphalt  ($/metric ton)
Base Price Index391.32

Fuel Price Adjustment
The Base Price Index (BPI) is a price index determined by arithmetic average of OPIS publications daily rack prices for the 28 calendar days preceding the bid opening.
28 Day AverageFuel  ($/gallon)
Base Price Index2.48


Archived Months for 2007
MonthFuelAsphalt
October2.75390.63
November3.01388.56
December2.73377.54

Archived Months for 2008
MonthFuelAsphalt
January2.65381.67
February2.81385.81
March3.36416.81
April3.54459.52
May3.93545.64
June4.10651.05

   


Home | About WFLHD | Projects | Procurement | Design Resources | Contact Information