Escalation Factors for OR PFH 37-1(6), Weston-Elgin Morning Creek Snowpark

Latest Month: October 2009
Asphalt Price: 468.00

Computation of Contract Base Price Index
Asphalt Cement Adjustment
The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.
4 Week AverageAsphalt  ($/US ton)
Base Price Index587.50


Archived Months for 2008
MonthAsphalt
December587.50

Archived Months for 2009
MonthAsphalt
January562.50
February562.50
March575.00
April550.00
May540.00
June502.50
July495.00
August490.00
September487.50

   


Home | About WFLHD | Projects | Procurement | Design Resources | Contact Information

USDOT | FHWA | FLHP | EFLHD | CFLHD | WFLHD

Please send your questions or comments to webmaster@mail.wfl.fhwa.dot.gov
Last update: November 3, 2009