![]() |
![]() |
| Location: Design > CADD Support > Geopak 2004 Guided Tour > Earthwork > Earthwork Converter | |
Earthwork Converter(Utility for importing Earthwork.txt file into Excel)Syntax at the bottom of the seed earthwork input file (V8_EARTHWORK.inp) and seed earthwork run (available using Geopak Project Manager) creates a “column based ASCII file” that can be imported into Excel and manipulated for providing adjusted earthwork volumes and creating sub-totals of various earthwork volumes for placement at the bottom of Plan/Profile sheets. More Information: The earthwork input file can be found on the server under X:\V8_Resource\X_30\Standards\Input_Files\ The seed earthwork run can be found on the server under X:\V8_Resource\X_30\Standards\Seed_runs\ The Excel workbook WFL_earthwork.xls can be found on the server under X:\V8_Resource\X_30\Standards\Bin and is composed of 3 worksheets:
NOTE:
This completes the process of importing the earthwork input file into the From Geopak worksheet. The column totals shown in Row 4 may be checked against your Geopak earthwork log file. To refresh the data in the worksheet, press the button, REFRESH Data. The macro will ask what file should be imported. By default the existing file will be chosen. Either select this file or find a different earthwork input file to import.
All data from the From Geopak worksheet is copied over to the Adjustments worksheet. Additional columns are also set up for manipulating the earthwork volume data. The additional columns include:
Using Subtotals:
Subtotals are typically required for defining areas of excavation/embankment and subsequent placement at the bottom of the Plan/Profile sheets. For example, if a subtotal is desired for Unadjusted Roadway Excavation from 50+000 to 50+300, then:
Using Shrink/Swell factors:
Normally, various soil types are encountered when constructing projects potentially resulting in varying shrink or sell factors. The Geotechnical report usually defines where these areas are located. Sandy material will shrink and rocky material will swell.
A generic shrink/swell factor may be entered on the spreadsheet (see cell D2) that relates to UNADJUSTED Roadway Excavation. Once this value is changed the entire D column inherits this value. It is possible to change this shrink/swell value as necessary in isolated cell ranges within column D to reflect other soil types. The results automatically appear in column E (ADJUSTED Roadway Excavation) and the Column E total is recalculated. For example, note that Station 50+140 through 50+260 uses a factor of 1.0 to calculate the Adjusted Rdwy Ex. The values in B14:B20 equals E14:E20.
Using the INSERT and DELETE row buttons:
Many projects require that “Added Quantities” from additional areas be added to the station ranges when placing the quantities on the Plan/Profile sheets. Since this workbook and its worksheets are protected (by default), it is not possible to simply insert or delete a row for additional volumes. The following buttons allow rows to be added or deleted:
|
|||||||||||||||
|
Home | About WFLHD | Projects | Procurement | Design Resources | Contact Information USDOT | FHWA | FLHP | EFLHD | CFLHD | WFLHD Please send your questions or comments to WFL.ProjDevMail@fhwa.dot.gov Last update: October 9, 2008 |
|||||||||||||||