Back to Staking NotesAPPLICATIONS > GEOPAK ROAD > CROSS SECTIONS > CROSS SECTION REPORTS CLEARING NOTES:
This brings up the XS Report palette. Click User and fill out the Report Header Dialog box. This Report Header information can be saved by clicking on File and selecting the path and file name to be saved. When finished, press Clearing on the XS Report palette.
This brings up the Clearing Report Dialog box as shown below:
- Key in the Job number and Chain.
- If you want notes for the entire chain, highlight the Beg Sta. field and press delete. The application will automatically set this field to the beginning station of the chain. Repeat this for the End Sta. Field. You may also simply key in a desired station range.
- Enter all the appropriate Existing Ground Line element symbology, either manually or by using the Select button, and identifying the elements graphically.
- Enter all the appropriate Proposed Finish Grade element symbology, either manually or by using the Select button, and identifying the elements graphically.
- Key in any desirable additional clearing distances as per your typical section.
- Adjust and set the desirable increment and subtotal settings for your notes.
If you have any Exception Widths, (no clearing areas) click on Except Width.
This brings up the Exception Width dialog box as shown below:
Press Add or Delete after each entry. After completing this step... these entry's can be saved for recalling later, by clicking on the File pulldown. Select the path and filename to save this information.
If you have any Additional areas (outside of the constuction limits) to be cleared, click on Additional Distance Via Station.
This brings up the Additional Distance Clearing dialog box as shown below:
Press Add, Modify or Delete after each entry. After completing this step... these entry's can be saved for recalling later, by clicking on the File pulldown. Select the path and filename to save this information.
Back at the Clearing Report Dialog box, click on File and select the path and file name for your Clearing notes.
I recommend that you toggle the Pause on Each XS option to ON.
When finished... Click Apply.
A partial sample of the notes are shown below:
10/02/98 PRA YELL 13(2) SECTION A EAST ENTRANCE ROAD Designer's Name Here CLEARING REPORT CUT SLOPE ROUNDING = 0.0000 m ADDITIONAL CLEARING IN CUT = 3.0000 m ADDITIONAL CLEARING IN FILL = 1.5000 m MINIMUM CLEARING WIDTH = 0.0000 m SUBTOTALS EVERY 700.0000 m . BEGINNING AT STATION 10+700 METHOD INCR ADDITIONAL CLEARING VIA STATION RANGE ............................. 11+000 TO 11+500 FOR LEFT SIDE = 10.000 m 11+800 TO 12+000 FOR RIGHT SIDE = 8.000 m 12+100 TO 12+500 FOR LEFT & RIGHT SIDES = 6.000 m ....................................................................... STATION CLEARING DISTANCE EXCEPTION AREA SUBTOTAL AREAS LT RT WIDTH m2 m2 HECTARES 10+020.00 R 1 11.720 10.628 0.000 451 10+040.00 R 1 11.920 10.760 0.000 462 10+060.00 R 1 12.104 11.384 0.000 472 10+080.00 R 1 12.142 11.477 0.000 479 10+100.00 R 1 12.401 11.872 0.000 486 10+120.00 R 1 12.470 11.855 0.000 490 10+140.00 R 1 12.439 12.166 0.000 504 10+160.00 R 1 12.631 13.068