Escalation Factors for Grand Loop Road, Canyon to Tower, Phase II

Project Number: WY PRA YELL 10(16)
Project Name: Grand Loop Road, Canyon to Tower, Phase II
Bid Opening Date: May 16, 2012

Base Price Indexes

Fuel

OPIS Report Location: Bozeman, Montana

Week / DateFuel  ($/gallon)
1 / April 243.36
2 / May 13.39
3 / May 83.40
4 / May 153.38
Base Price Index3.38

Asphalt Cement

Asphalt Weekly Location: Northern, WY

Week / DateAsphalt  ($/ton)
1 / April 24611.78
2 / May 1611.78
3 / May 8611.78
4 / May 15611.78
Base Price Index611.78

Computation Approaches Used to Determine Base Price Indexes

Asphalt Cement Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.

Fuel Price Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average of OPIS publications' daily rack prices on a weekly basis for the 4 weeks preceding the bid opening.